Floor area method estimating

This estimate is an approximate cost obtained by using anestimated price for each unit of groos floor area. This method of estimatingfacilities costs is frequently used in building and residential homeconstruction.
The main reason for the popularity of the floor area method is its simplicity.There are few rules to remember and the cost per square metre is well understood by property developers.A proposed building is measured at each floor level (between inside faces of external walls);no deductions are made for internal walls,stairs or lift zones.Previous similar building costs are used by dividing the construction cost by the internal floor area.Adjustments can be made for location and inflation; but specification adjustments are much more difficult to estimate.Subjective judgements are made for size,shape,number of storeys,services,ground conditions and standard of finishes.A separate assessment should be made for external works,demolitions, incoming services and drainage which can be significantly different for similar buildings.
There are many buildings where the unit of accommodation method is impracticable;such as warehouse projects or open-plan offices.In these cases the superficial floor area method is found to be reliable with an accuracy of 10% to 15%.This method also works well with certain external works contracts such as concrete paving or macadam surfacing.
Sometimes contractors are asked to quote for building work using sketch drawing sand a square metre price.It is unlikely that a contractor would risk signing a contract on this basis.First a clear scope of works would be needed together with a site survey and soil investigation report.The price must accurately reflect the amount and specification of works.